1
UPCC Implementation
1
  • Alyssa Washington
11/1/2024
12/20/2024
36 days
MOIS Implementation & Optimization
dummy-label
66%
Urgent
2
Fort St James
5
12/14
9/4/2024
12/20/2024
78 days
MOIS Implementation & Optimization
dummy-label
100%
Important
3
Prince George Renal
1
2/6
6/3/2024
3/11/2025
202 days
MOIS Implementation & Optimization
dummy-label
0%
Medium
4
Needle Exchange Prince George
1
8/30/2024
1/31/2025
111 days
MOIS Implementation & Optimization
dummy-label
0%
Medium
5
Prince George MS Clinic
1
0/7
8/30/2024
1/31/2025
111 days
MOIS Implementation & Optimization
dummy-label
0%
Medium
6
AMC Application Management Committee
11/29/2024
12/29/2028
1066 days
Other Elder Services Projects
dummy-label
0%
Medium
7
Rupert Primary Mobile Clinic
1
1/6
11/13/2024
2/6/2025
62 days
MOIS Implementation & Optimization
dummy-label
0%
Medium
8
NW SUS
    MOIS Implementation & Optimization
    dummy-label
    0%
    Medium
    9
    FJN IceAlerts
      MOIS Implementation & Optimization
      dummy-label
      0%
      Medium
      10
      Home Support Redesign Board
      1
      11/29/2024
      8/8/2025
      181 days
      Home Support Redesign Project
      dummy-label
      0%
      Important
      11
      Procura To Alayacare Board
      11/29/2024
      12/31/2027
      806 days
      Procura to Alayacare Project
      dummy-label
      0%
      Important
      12
      HSAC Home Support Advisory Committee
      11/29/2024
      12/29/2028
      1066 days
      Other Elder Services Projects
      dummy-label
      0%
      Medium
      13
      Report Enhancement WG
      MOIS Operational
      dummy-label
      0%
      Medium
      14
      NHR Long Term Care Waitlist Improvement Project (LTCH WL)
      11/29/2024
      12/31/2025
      284 days
      Other Elder Services Projects
      dummy-label
      25%
      Medium
      15
      InterRAI Reporting System IRRS
      11/29/2024
      12/31/2026
      545 days
      Other Elder Services Projects
      dummy-label
      0%
      Medium
      16
      Community and LTCH Transitions (LTCH AD)
      • Janis Morris
      11/29/2024
      12/26/2025
      281 days
      Other Elder Services Projects
      dummy-label
      0%
      Medium
      17
      Pixalere PIA
      • Janis Morris
      11/29/2024
      12/26/2025
      281 days
      Pixalere / Momentum Operational
      dummy-label
      50%
      Medium
      18
      Pixalere Upgrade and Enhancement
      1
      4/18
      • Janis Morris
      11/29/2024
      Today
      216 days
      Pixalere / Momentum Operational
      dummy-label
      42%
      Medium
      19
      HCC MRR Period Reporting & HS Dashboard
      11/28/2024
      5/14/2026
      381 days
      Other Elder Services Projects
      dummy-label
      0%
      Medium
      20
      HSS/HSTL Smithers Implementation
      2/14/2025
      12/31/2025
      229 days
      MOIS Implementation & Optimization
      dummy-label
      10%
      Medium
      21
      Palliative Registry Procura to MOIS
      11/10/2025
      2/27/2026
      80 days
      MOIS Implementation & Optimization
      dummy-label
      5%
      Medium